超高层彩钢结构施工有哪些技巧
1施工前准备
高层彩钢框架结构安装前的准备工作,除了一般的准备工作外,还包括:钢结构构件的预检查与匹配、钢柱基础的检查、安装流程部分的划分、安装机械的选择等。钢构件在加工厂的工艺流程如下:一是编制构件制造说明书,对原材料进行校正;二是放样、下料、切割等施工;制孔、边缘加工;组装焊接后,认真进行端部加工和摩擦表面处理,严格执行除锈、涂装步骤,最终完成验收发运。
2测量和定位
高层彩钢框架结构测量定位是施工中不可忽视的问题。这一过程不仅是
高层彩钢框架结构的准确定位,而且关系到整个钢结构安装的质量和进度,与测量工作的质量密切相关。因此,在钢结构施工项目中,应积极采用先进的测量仪器,主要针对高层钢结构施工的难点和重点,充分利用工程施工经验,并紧密结合高层钢结构施工特点,对钢结构吊装焊接质量进行正确指导和实时监控。
2.1测量控制内容
高层彩钢框架结构安装测量工作的主要内容:土建工程平面控制基线或红线边界桩位和高程基准点位置的验收是正确的,并作出书面记录;基础埋置部位的设置和标高;底板组立、构件安装标高、轴线的设置与控制;合理建立主轴网;平面控制网放样;高程测量;H型钢柱及箱型柱的校正。
2.2测量控制的基本方法
钢柱测控:采用全站仪检查轴线偏差、经纬仪校正垂直度相结合的控制方法;高程传递:常规的高程传递测量方法可直接用大直尺进行;平面控制网测量放线:根据施工现场的能见度情况,先测量主控制轴线,再加密建筑轴线;平面控制网铅垂测量:平面控制网铅垂测量采用激光管道机对已测得的轴线控制点进行铅垂。
1. Preparation before construction
The preparatory work before the installation of high-rise steel frame structure, in addition to the general preparatory work, also includes: pre inspection and matching of steel structure components, inspection of steel column foundation, division of
installation flow section, selection of installation machinery, etc. The manufacturing procedures of steel components in the processing plant are as follows: firstly, the preparation of component manufacturing instructions and the correction of raw materials;
secondly, the lofting, blanking, cutting and other construction; hole making and edge processing; after assembly and welding, the end processing and friction surface treatment are carefully carried out, and the derusting and coating steps are strictly
implemented, and finally the acceptance and shipment can be completed.
2. Measurement and positioning
Surveying and positioning is a matter that can not be ignored in construction. This process is not only the accurate positioning of steel
structure deformation control, but also the quality and progress of the overall steel structure installation, which is closely related to the quality of the measurement work. Therefore, in the steel structure construction project, we should actively use
advanced measuring instruments, mainly aiming at the difficulties and key points of high-rise steel structure construction, and make full use of the engineering construction experience, And closely combined with the characteristics of high-rise steel
structure construction, the hoisting and welding quality of steel structure are correctly guided and real-time monitored.
2.1 measurement control content
The main contents of steel frame structure installation survey work: acceptance of civil
engineering plane control baseline or red line boundary stake point and elevation datum point position is correct, and make written records; foundation embedded parts setting out in place and elevation; setting and controlling the elevation and axis of
base plate group and component installation; reasonable establishment of main axis network; plane control network setting out; elevation measurement; H-beam column And the correction of box column.
2.2 basic methods of measurement control
Steel column measurement and control: adopt the control method combining the total station to check the axis deviation and theodolite to correct the verticality; elevation transfer: the conventional measurement method of elevation transfer can be directly
carried out with a large ruler; the measurement and setting out of horizontal control network: according to the visibility conditions of the construction site, the main control axis is measured first, and then the building axes are encrypted; the vertical
lead survey of horizontal control network: make the vertical lead survey of horizontal control network Use laser plumber to plumb the axis control points that have been measured.